Tuesday, February 9, 2016

Framing Day 5 - Enclosing the Roof, Trusses over the Garage

Framing Day 5 - Enclosing the Roof, Trusses over the Garage

Framing Day 5 has completed!

Pulling up to the house I could see that they finished putting the trusses above the garage and kitchen area. They had also started on the front peak above the garage but this was not finished. Almost all of the sheathing appears to be on the exterior of the house except for a few pieces.

Curt had originally told me that they should be finishing all of the framing by tomorrow, I am not sure they are going to be able to finish everything that needs done.... Some of the things that I noticed which still need framed up are
  1. Porch Roof
  2. Garage Peak
  3. Basement Stairs
  4. Master Bedroom Wall
  5. Wrap the Entire House
  6. Tar Paper the Roof
  7. Install Windows
  8. Install Exterior Doors
  9. Take out closet in Mudroom

Only time will tell and I am hoping Curt is right and all of the framing is done tomorrow. Here are some of the picture from Day 5.

Front of the house, almost all of the sheathing is complete!

Backside of the house looks like they started to tar paper the back of the roof

Right side of the house - The peak on the garage needs finished and more sheathing in blake's room

Left side of the house

Looking into the Garage with a roof!

Looking into the trusses from inside the house

 Looking at the rafters above the kitchen

 Looking into the rafters over the garage/kitchen area