Start of Hanging Dry-wall, Heater Assembled, Natural Gas Ran
Sorry everyone I got a
little behind at the end of last week as I was running Ethernet and insulating
the garage and certain interior walls every day after work... Not much progress took
place last week as we were waiting for the hangers to put up the drywall and
they were not able to start until Friday. Basically they began dry-walling the
ceilings in the house, they finished the upstairs and the kitchen ceilings. The
heater was assembled down in the basement but still not all of the piping is
complete yet... The gas company stopped by on Friday and they were able to run
the gas line from the road to the house.
Can light closeup in second story hallway
Kitchen/Dining Room Ceiling Dry-Wall
Second Story Ceiling Dry-Wall
Kids Room 1 Ceiling Dry-walled
Kids Room 2 Ceiling Dry-walled
Heater
Piping for the Heater
Heater Partially Assembled
White Flags to mark out where Electrical will run
Gas Line ran up to the house