Footers

The last couple of weeks have been crawling by it seems like. We are currently about 2 weeks behind schedule due to some uncontrollable circumstances, first we had a huge rain storm the week after new years which we had to pump out about 2 foot of water, then last week and this week we have been running into issues with mother nature and extremely cold temps. Just one of the joys of deciding to start building during the middle of winter :) 

Although we have had a bit of progress and we have been able to at least get the footers installed and covered with stone. Unfortunately I was out of town for work so I wasn't able to get a lot of good pictures... 

Pictures of the "Pit" & the framing of the footers



Pictures of the footers covered with stone